Perform Quantitative Risk Analysis focuses on:
A.
compiling a list of known risks and preparing responses to them.
B.
assessing the probability of occurrence and Impact for every risk in the risk register.
C.
evaluating the contingency and management reserves required for the project.
D.
analyzing numerically the impact of individual risks on the overall project's time and cost objectives.