Question 767 - CAPM discussion
In an agile or adaptive environment. when should risk be monitored and prioritized?
A.
Only during the initiation and Closing phases
B.
During the initiation and Planning phases
C.
During each iteration as the project progresses
D.
Throughout the Planning process group and retrospective meeting