Which group of inputs will a project manager use during the Monitor Stakeholder Engagement process?

A.
Project charter, business documents, and project management plan
Answers
A.
Project charter, business documents, and project management plan
B.
Agreements, scope baseline, and project management plan
Answers
B.
Agreements, scope baseline, and project management plan
C.
Project charter, business case, and project management plan
Answers
C.
Project charter, business case, and project management plan
D.
Work performance data, enterprise environmental factors, and project management plan
Answers
D.
Work performance data, enterprise environmental factors, and project management plan
Suggested answer: D