Which of the following sets are inputs to the Collect Requirements process?

A.
Project charter and requirements documentation
Answers
A.
Project charter and requirements documentation
B.
Project charter and business documents
Answers
B.
Project charter and business documents
C.
Project charter and stakeholder requirements
Answers
C.
Project charter and stakeholder requirements
D.
Business documents and requirements traceability matrix
Answers
D.
Business documents and requirements traceability matrix
Suggested answer: B