A project manager Is addressing risks and potential concerns related to stakeholder management, and Is clarifying and resolving previously Identified issues. In which process is the project manager engaged?
A.
Identify Stakeholders
B.
Plan Stakeholder Engagement
C.
Manage Stakeholder Engagement
D.
Monitor Slakeholder Engagement