A project manager needs to demonstrate that the project meets quality standards and success criteri a. For that reason, the project manager is defining the quality objectives of the project, the quality tools that will be used, and quality metrics for the project deliverables.
Which process is the project manager executing?
A.
Manage Quality
B.
Plan Quality Management
C.
Control Quality
D.
Plan Scope Management