Question 838 - CAPM discussion

Report
Export

What is a tailoring consideration for the application of Project Risk Management processes?

A.
Project complexity
Answers
A.
Project complexity
B.
Procurement criteria
Answers
B.
Procurement criteria
C.
Communication technology
Answers
C.
Communication technology
D.
Knowledge management
Answers
D.
Knowledge management
Suggested answer: A