A project manager is launching an information system to provide a lessons learned database. This action is necessary for recipients to access content at their own discretion. Which communication method is described?

A.
Push communication
Answers
A.
Push communication
B.
Pull communication
Answers
B.
Pull communication
C.
Interactive communication
Answers
C.
Interactive communication
D.
Stakeholder communication
Answers
D.
Stakeholder communication
Suggested answer: B