Question 846 - CAPM discussion
A project manager is launching an information system to provide a lessons learned database. This action is necessary for recipients to access content at their own discretion. Which communication method is described?
A.
Push communication
B.
Pull communication
C.
Interactive communication
D.
Stakeholder communication