Which of the following is used as an input to prepare a cost management plan?

A.
Expert judgment
Answers
A.
Expert judgment
B.
Lessons learned
Answers
B.
Lessons learned
C.
Cost estimates
Answers
C.
Cost estimates
D.
Project management plan
Answers
D.
Project management plan