Question 852 - CAPM discussion
Which two processes should be used to influence costs in the early stages of a project?
A.
Estimate Costs and Determine Budget
B.
Plan Cost Management and Estimate Activity Durations
C.
Control Quality and Control Costs
D.
Plan Stakeholder Engagement and Plan Communications Management