Question 856 - CAPM discussion
Analyzing activity sequences, durations, resource requirements, and schedule constraints for project execution and monitoring and controlling relates to which process?
A.
Develop Schedule
B.
Control Schedule
C.
Estimate Activity Durations
D.
Define Activities
Your answer: