Analyzing activity sequences, durations, resource requirements, and schedule constraints for project execution and monitoring and controlling relates to which process?

A.
Develop Schedule
Answers
A.
Develop Schedule
B.
Control Schedule
Answers
B.
Control Schedule
C.
Estimate Activity Durations
Answers
C.
Estimate Activity Durations
D.
Define Activities
Answers
D.
Define Activities
Suggested answer: A