A project manager is monitoring and recording results of executing the quality management activities to assess performance and ensure the project outputs are complete, correct, and meet customer expectations. Which output is the project manager using?

A.
Approved change requests
Answers
A.
Approved change requests
B.
Verified deliverables
Answers
B.
Verified deliverables
C.
Lessons learned
Answers
C.
Lessons learned
D.
Work performance data
Answers
D.
Work performance data
Suggested answer: B