A project manager is monitoring and recording results of executing the quality management activities to assess performance and ensure the project outputs are complete, correct, and meet customer expectations. Which output is the project manager using?
A.
Approved change requests
B.
Verified deliverables
C.
Lessons learned
D.
Work performance data