During the execution phase of a project a detect is found. The project manager takes responsibility and with the correct documentation, begins the task necessary to repair the defect. What process was applied?

A.
Change request
Answers
A.
Change request
B.
Risk response
Answers
B.
Risk response
C.
Risk management plan
Answers
C.
Risk management plan
D.
Lessons learned
Answers
D.
Lessons learned
Suggested answer: A