In an adaptive or agile life cycle, how are the customer and sponsor involved in the project scope management activities?

A.
Involvement is needed only during project initiation.
Answers
A.
Involvement is needed only during project initiation.
B.
Minimal involvement of stakeholders is sufficient.
Answers
B.
Minimal involvement of stakeholders is sufficient.
C.
They should be continuously engaged.
Answers
C.
They should be continuously engaged.
D.
They should be involved only during phase or deliverable reviews.
Answers
D.
They should be involved only during phase or deliverable reviews.
Suggested answer: C