A project manager needs to tailor the Project Cost Management process. Which considerations should the project manager apply?

A.
Diversity background
Answers
A.
Diversity background
B.
Stakeholder's relationships
Answers
B.
Stakeholder's relationships
C.
Technical expertise
Answers
C.
Technical expertise
D.
Knowledge management
Answers
D.
Knowledge management
Suggested answer: D