Question 898 - CAPM discussion

Report
Export

The project manager is using co-location and providing training to the project team. On which of the following Project Resource Management processes is the project manager working?

A.
Acquire Resources
Answers
A.
Acquire Resources
B.
Control Resources
Answers
B.
Control Resources
C.
Manage Team
Answers
C.
Manage Team
D.
Develop Team
Answers
D.
Develop Team
Suggested answer: D