Question 905 - CAPM discussion
Which of the following are outputs of the Define Scope process in Project Scope Management?
A.
Requirements documentation and requirements traceability matrix
B.
Scope management plan and requirements management plan
C.
Project scope statement and project documents updates
D.
Scope baseline and project documents updates