Which of the following are outputs of the Define Scope process in Project Scope Management?

A.
Requirements documentation and requirements traceability matrix
Answers
A.
Requirements documentation and requirements traceability matrix
B.
Scope management plan and requirements management plan
Answers
B.
Scope management plan and requirements management plan
C.
Project scope statement and project documents updates
Answers
C.
Project scope statement and project documents updates
D.
Scope baseline and project documents updates
Answers
D.
Scope baseline and project documents updates
Suggested answer: D