For which is the Scrum Master responsible?

A.
Managing the performance of the Scrum Team.
Answers
A.
Managing the performance of the Scrum Team.
B.
The meetings and the objectives that a Scrum Team sets for itself.
Answers
B.
The meetings and the objectives that a Scrum Team sets for itself.
C.
The Scrum framework being adopted and used properly.
Answers
C.
The Scrum framework being adopted and used properly.
D.
Keeping track of resource allocation.
Answers
D.
Keeping track of resource allocation.
Suggested answer: C