When can a Development Team cancel a Sprint?

A.
It can't. Only Product Owners can cancel Sprints.
Answers
A.
It can't. Only Product Owners can cancel Sprints.
B.
When functional expectations are not well understood.
Answers
B.
When functional expectations are not well understood.
C.
When the Product Owner is absent too often.
Answers
C.
When the Product Owner is absent too often.
D.
When the selected Product Backlog items for the Sprint become unachievable.
Answers
D.
When the selected Product Backlog items for the Sprint become unachievable.
E.
When a technical dependency cannot be resolved.
Answers
E.
When a technical dependency cannot be resolved.
Suggested answer: A