True or False: An increment must be released to customers or users at the end of each sprint.

A.
True
A.
True
Answers
B.
False
B.
False
Answers
Suggested answer: B

Explanation:

According to the Scrum Guide, an Increment does not have to be released to customers or users at the end of each Sprint. However, it must be in a usable condition and meet the Definition of Done.

The decision to release an Increment is made by the Product Owner, based on the value and feedback obtained from stakeholders. The other option is not valid, as it implies that releasing an Increment is mandatory at the end of each Sprint.

What does n mean tor a scrum Team to be cross-function at? (choose the best answer)

A.
The Scrum Team includes skilled individuals who together have all the skins necessary to create value each sprint
A.
The Scrum Team includes skilled individuals who together have all the skins necessary to create value each sprint
Answers
B.
Developers on the Scrum Team work closely with business analysis architects developers, and testers who are not on the team
B.
Developers on the Scrum Team work closely with business analysis architects developers, and testers who are not on the team
Answers
C.
The Scrum Team includes not only developers but also business analysts, architects, and testers
C.
The Scrum Team includes not only developers but also business analysts, architects, and testers
Answers
D.
The Scrum Team is a virtual team drawing from separate teams of business analysts, architects, developers, and testers
D.
The Scrum Team is a virtual team drawing from separate teams of business analysts, architects, developers, and testers
Answers
Suggested answer: A

Explanation:

According to the Scrum Guide, a Scrum Team is cross-functional if it includes skilled individuals who together have all the skills necessary to create value each Sprint. This means that the Developers can work on any aspect of the product without depending on others outside the team. The other options are not valid descriptions of cross-functionality, as they either imply that the Developers work in silos or rely on external people (such as business analysts, architects, testers, or separate teams).

True or False: The purpose of a Sprint Is lo produce a valuable useful Inclement.

A.
True
A.
True
Answers
B.
False
B.
False
Answers
Suggested answer: A

Explanation:

According to the Scrum Guide, the purpose of a Sprint is to produce a valuable useful Increment that meets the Definition of Done and the Sprint Goal. This means that the Developers work on items from the Product Backlog that deliver value to the stakeholders and align with the product vision.

The other option is not valid, as it implies that producing an Increment is not the purpose of a Sprint.

Who does the work to make sure Product Backlog items conform to the Definition of Done?

(choose the Best answer)

A.
The Quality Assurance Team
A.
The Quality Assurance Team
Answers
B.
The Scrum Team
B.
The Scrum Team
Answers
C.
The Product Owner
C.
The Product Owner
Answers
D.
The Scrum Master
D.
The Scrum Master
Answers
E.
The Developers
E.
The Developers
Answers
Suggested answer: E

Explanation:

According to the Scrum Guide, the Developers do the work to make sure Product Backlog items conform to the Definition of Done, as they are responsible for creating a "Done" Increment that meets the Definition of Done. The other options are not valid, as they imply that the work is done by someone else outside the Development Team (such as Quality Assurance Team) or by another role on the Scrum Team (such as Product Owner or Scrum Master).

Who determines how many Product Backlog items the Developers select tor a sprint? (choose the best answer)

A.
The Scrum Master
A.
The Scrum Master
Answers
B.
The Scrum Team
B.
The Scrum Team
Answers
C.
The Developers
C.
The Developers
Answers
D.
The stakeholders attending Sprint Planning
D.
The stakeholders attending Sprint Planning
Answers
E.
The Product Owner
E.
The Product Owner
Answers
Suggested answer: C

Explanation:

The Developers determine how many Product Backlog items they select for a Sprint, as stated in the Scrum Guide: "The Developers select items from the Product Backlog to include in the current Sprint.

The Scrum Team may refine these items during this process, which increases understanding and confidence."

When does a Developer become accountable for an item in the sprint Backlog?

(choose the best answer)

A.
During the Daily Scrum
A.
During the Daily Scrum
Answers
B.
Never am Developers on the Scrum Team share accountability tor items in the
B.
Never am Developers on the Scrum Team share accountability tor items in the
Answers
C.
As soon as a Developer on the Scrum Team can accommodate more work
C.
As soon as a Developer on the Scrum Team can accommodate more work
Answers
D.
At Sprint Planning when all of the Sprint Backlog items are split evenly across the Developers
D.
At Sprint Planning when all of the Sprint Backlog items are split evenly across the Developers
Answers
Suggested answer: B

Explanation:

A Developer becomes accountable for an item in the Sprint Backlog never as Developers on the Scrum Team share accountability for items in the Sprint Backlog, as stated in the Scrum Guide: "The Developers can select whatever items they want as long as they feel they can complete the work by the end of the Sprint. The Scrum Team is responsible for all estimates. The Product Owner may influence the Developers by helping them understand and select trade-offs, but the people who will perform the work make the final estimate."

True or False: A scrum Master Fulfills me same role as a traditional project Manager.

A.
True
A.
True
Answers
B.
False
B.
False
Answers
Suggested answer: B

Explanation:

A Scrum Master fulfills a different role than a traditional project manager, as stated in 2: "A project manager helps manage the project timeline, resources, and scope in order to meet business requirements. A Scrum Master, however, helps ensure the Scrum Team follows Scrum theory, practices, and rules. The Scrum Master is a servant-leader who helps optimize the value created by the Scrum Team."

During the Sprint. Me Scrum Master's role is to do which two of the following: (choose the best two answers)

A.
Facilitate inspection and adaptation opportunities as requested or needed
A.
Facilitate inspection and adaptation opportunities as requested or needed
Answers
B.
Coaching the team members in self-management
B.
Coaching the team members in self-management
Answers
C.
Ensure the Product Owner attends all scrum events.
C.
Ensure the Product Owner attends all scrum events.
Answers
D.
Escalate team conflicts to functional line managers
D.
Escalate team conflicts to functional line managers
Answers
E.
Monitor the progress of the Developers
E.
Monitor the progress of the Developers
Answers
F.
Assign tasks with the Scrum team.
F.
Assign tasks with the Scrum team.
Answers
Suggested answer: A, B

Explanation:

During the Sprint, the Scrum Master's role is to facilitate inspection and adaptation opportunities as requested or needed, and to coach the team members in self-management, as stated in 3: "The Scrum Master is accountable for establishing Scrum as defined in the Scrum Guide. They do this by helping everyone understand Scrum theory and practice, both within the Scrum Team and the organization. The Scrum Master is accountable for the Scrum Team's effectiveness. They do this by enabling the Scrum Team to improve its practices, within the Scrum framework."

What is the timebox for the sprint Review? (choose the best answer)

A.
1 day
A.
1 day
Answers
B.
4 hours for a one-month Sprint.
B.
4 hours for a one-month Sprint.
Answers
C.
As long as needed
C.
As long as needed
Answers
D.
2 hours for a one-month Sprint.
D.
2 hours for a one-month Sprint.
Answers
Suggested answer: B

Explanation:

The timebox for the Sprint Review is four hours for a one-month Sprint, as stated in [4]: "The Sprint Review is held at the end of the Sprint to inspect the Increment and adapt the Product Backlog if needed. During the event, the Scrum Team and stakeholders review what was accomplished in the Sprint and what has changed in their environment. Based on this information, attendees collaborate on what to do next. The Product Owner explains what Product Backlog items have been "Done" and what has not been "Done"; additionally, they discuss any changes to scope or budget or potential value. The entire group then collaborates on what to do next, so that the Sprint Review provides valuable input to subsequent Sprint Planning. The Sprint Review is a working session and attendees should inspect based on facts. A Sprint Review is held at the end of every Sprint for a maximum duration of four hours for a one-month Sprint."

When is a Product Backlog item considered complete? (choose the best answer)

A.
When the item passes ail acceptance criteria
A.
When the item passes ail acceptance criteria
Answers
B.
When the item has gamed product sponsor approval
B.
When the item has gamed product sponsor approval
Answers
C.
At the end of the Sprint
C.
At the end of the Sprint
Answers
D.
When the item meets the Definition of Done
D.
When the item meets the Definition of Done
Answers
Suggested answer: D

Explanation:

A Product Backlog item is considered complete when it meets the Definition of Done, as stated in [5]:

"When a Product Backlog item or an Increment is described as "Done", everyone must understand what "Done" means. Although this varies significantly per Scrum Team, members must have a shared understanding of what it means for work to be complete, to ensure transparency. This is the definition of "Done" for the Scrum Team and is used to assess when work is complete on the product Increment."

Total 250 questions
Go to page: of 25