ExamGecko
Question list
Search
Search

Question 9 - PSM I discussion

Report
Export

In the Sprint Planning meeting, the Product Owner and the Development Team were unable to reach a clear understanding about the highest order Product Backlog items. Because of this, the Development Team couldn't figure out how many Product Backlog items it could forecast for the upcoming Sprint. They were able to agree on a Sprint Goal, however.

Which of the following two actions should the Scrum Master support? (Choose two.)

A.
Cancel the Sprint. Send the entire team to an advanced Scrum training and then start a new Sprint.
Answers
A.
Cancel the Sprint. Send the entire team to an advanced Scrum training and then start a new Sprint.
B.
Forecast the most likely Product Backlog items to meet the goal and create a Sprint Backlog based on a likely initial design and plan. Once the time-box for the Sprint Planning meeting is over, start the Sprint and continue to analyze,decompose, and create additional functionality during the Sprint.
Answers
B.
Forecast the most likely Product Backlog items to meet the goal and create a Sprint Backlog based on a likely initial design and plan. Once the time-box for the Sprint Planning meeting is over, start the Sprint and continue to analyze,decompose, and create additional functionality during the Sprint.
C.
Continue the Sprint Planning meeting past its time-box until an adequate number of Product Backlog items are well enough understood for the DevelopmentTeam to make a complete forecast. Then start the Sprint.
Answers
C.
Continue the Sprint Planning meeting past its time-box until an adequate number of Product Backlog items are well enough understood for the DevelopmentTeam to make a complete forecast. Then start the Sprint.
D.
Discuss in the upcoming Sprint Retrospective why this happened and what changes will make it less likely to recur.
Answers
D.
Discuss in the upcoming Sprint Retrospective why this happened and what changes will make it less likely to recur.
E.
Ask everyone to take as much time as needed to analyze the Product Backlog first, and then reconvene another Sprint Planning meeting.
Answers
E.
Ask everyone to take as much time as needed to analyze the Product Backlog first, and then reconvene another Sprint Planning meeting.
Suggested answer: B, D
asked 23/09/2024
Archana Pingily
34 questions
User
Your answer:
0 comments
Sorted by

Leave a comment first