Which output from Sprint Planning provides the Development Team with a target and overarching direction for the Sprint?

A.
The Sprint Backlog.
Answers
A.
The Sprint Backlog.
B.
The Sprint Goal
Answers
B.
The Sprint Goal
C.
The release plan.
Answers
C.
The release plan.
D.
Sprint Review minutes.
Answers
D.
Sprint Review minutes.
Suggested answer: B