Question 32 - PSM I discussion
What is the main reason for the Scrum Master to be at the Daily Scrum?
A.
To gather status and progress information to report to management.
B.
To write down any changes to the Sprint Backlog, including adding new items, and tracking progress on the burn-down.
C.
He or she does not have to be there; he or she only has to ensure the Development Team has a Daily Scrum.
D.
To make sure every team member answers the three questions.