How often should Development Team membership change?

A.
As needed, while taking into account a short term reduction in productivity.
Answers
A.
As needed, while taking into account a short term reduction in productivity.
B.
Never, because it reduces productivity.
Answers
B.
Never, because it reduces productivity.
C.
As needed, with no special allowance for changes in productivity.
Answers
C.
As needed, with no special allowance for changes in productivity.
D.
Every Sprint to promote shared learning.
Answers
D.
Every Sprint to promote shared learning.
Suggested answer: A