The time-box for a Daily Scrum is:

A.
Two minutes per person.
Answers
A.
Two minutes per person.
B.
15 minutes.
Answers
B.
15 minutes.
C.
15 minutes for a 4 week sprint. For shorter Sprints it is usually shorter.
Answers
C.
15 minutes for a 4 week sprint. For shorter Sprints it is usually shorter.
D.
4 hours.
Answers
D.
4 hours.
E.
The same time of day every day.
Answers
E.
The same time of day every day.
Suggested answer: B