Every Scrum team must have a Product Owner and Scrum Master.

A.
True. Outcomes affected by their participation and availability.
Answers
A.
True. Outcomes affected by their participation and availability.
B.
False. A Product Owner can be replaced by a business analyst in the Development Team.
Answers
B.
False. A Product Owner can be replaced by a business analyst in the Development Team.
C.
False. A Scrum Master is only required when asked for by the Development Team.
Answers
C.
False. A Scrum Master is only required when asked for by the Development Team.
D.
True. Each must be 100% dedicated to the Scrum Team.
Answers
D.
True. Each must be 100% dedicated to the Scrum Team.
Suggested answer: A