Which three purposes does the definition of "Done" serve? (Choose the best three answers.)
A.
Guide the Development Team on how many Product Backlog items to select for the Sprint.
B.
Create a shared understanding of when work is complete.
C.
Describe the purpose, objective, and time-box of each Scrum event.
D.
Describe the work that must be done before the Sprint is allowed to end.
E.
Increase transparency.