Which statement best describes the Sprint Review? (Choose the best answer.)

A.
It is used to congratulate the Development Team if it did what it forecast, or to punish the Development Team if it failed to meet its forecast.
Answers
A.
It is used to congratulate the Development Team if it did what it forecast, or to punish the Development Team if it failed to meet its forecast.
B.
It is a demo at the end of the Sprint for everyone in the organization to check on the work done.
Answers
B.
It is a demo at the end of the Sprint for everyone in the organization to check on the work done.
C.
It is a mechanism to control the Development Team's activities during a Sprint.
Answers
C.
It is a mechanism to control the Development Team's activities during a Sprint.
D.
It is when the Scrum Team and stakeholders inspect the outcome of a Sprint and figure out what to do next.
Answers
D.
It is when the Scrum Team and stakeholders inspect the outcome of a Sprint and figure out what to do next.
Suggested answer: D