List of questions
Related questions
Question 110 - PSM I discussion
Which statement best describes the Sprint Review? (Choose the best answer.)
A.
It is used to congratulate the Development Team if it did what it forecast, or to punish the Development Team if it failed to meet its forecast.
B.
It is a demo at the end of the Sprint for everyone in the organization to check on the work done.
C.
It is a mechanism to control the Development Team's activities during a Sprint.
D.
It is when the Scrum Team and stakeholders inspect the outcome of a Sprint and figure out what to do next.
Your answer:
0 comments
Sorted by
Leave a comment first