A member of the Development Team takes the Scrum Master aside to express his concerns about data security issues. What should the Scrum Master do?

A.
Add security to the definition of "Done".
Answers
A.
Add security to the definition of "Done".
B.
Tell the Product Owner to stop further development of features until the issues are fixed.
Answers
B.
Tell the Product Owner to stop further development of features until the issues are fixed.
C.
Create a Product Backlog item for security.
Answers
C.
Create a Product Backlog item for security.
D.
Go check with the testers.
Answers
D.
Go check with the testers.
E.
Ask the person to share the issue with the team as soon as possible.
Answers
E.
Ask the person to share the issue with the team as soon as possible.
Suggested answer: E