You have just been hired by a company new to Scrum. Your management has assigned you to be the Scrum Master of six new Scrum Teams. These teams will build one product. Select two conditions you should strive for in this scenario.

(Choose two.)

A.
There should be six Product Owners, one for each Scrum Team.
Answers
A.
There should be six Product Owners, one for each Scrum Team.
B.
There should be six Product Owners, reporting to a chief Product Owner.
Answers
B.
There should be six Product Owners, reporting to a chief Product Owner.
C.
The product has one Product Backlog.
Answers
C.
The product has one Product Backlog.
D.
Each Scrum Team should have a separate Product Backlog.
Answers
D.
Each Scrum Team should have a separate Product Backlog.
E.
There should be only one Product Owner.
Answers
E.
There should be only one Product Owner.
Suggested answer: C, E