Which of the following is a Developer accountable for? (Choose the best two answers.)

A.
Selecting the Product Owner.
Answers
A.
Selecting the Product Owner.
B.
Reporting productivity.
Answers
B.
Reporting productivity.
C.
Creating a plan for the Sprint, the Sprint Backlog.
Answers
C.
Creating a plan for the Sprint, the Sprint Backlog.
D.
Organizing the work required to meet the Sprint Goal.
Answers
D.
Organizing the work required to meet the Sprint Goal.
Suggested answer: C, D