Question 192 - PSM I discussion
A Product Owner wants advice from the Scrum Master about estimating work in Scrum. Which of these is the guideline that a Scrum Master should give?
(Choose the best answer.)
A.
Product Backlog items must be estimated in story points.
B.
Estimates are made by the people doing the work.
C.
Estimates must be in relative units.
D.
Scrum forbids estimating.
E.
Estimates are made by the Product Owner, but are best checked with the Development Team.
Your answer: