Which three of the following are time-boxed events in Scrum? (Choose the best three answers.)

A.
Release Planning.
Answers
A.
Release Planning.
B.
Release Retrospective.
Answers
B.
Release Retrospective.
C.
Sprint Retrospective.
Answers
C.
Sprint Retrospective.
D.
Sprint Planning.
Answers
D.
Sprint Planning.
E.
Sprint Testing.
Answers
E.
Sprint Testing.
F.
Sprint 0.
Answers
F.
Sprint 0.
G.
Daily Scrum.
Answers
G.
Daily Scrum.
Suggested answer: C, D, G