True or False: An increment must be released to customers or users at the end of each sprint.

A.
True
Answers
A.
True
B.
False
Answers
B.
False
Suggested answer: B

Explanation:

According to the Scrum Guide, an Increment does not have to be released to customers or users at the end of each Sprint. However, it must be in a usable condition and meet the Definition of Done.

The decision to release an Increment is made by the Product Owner, based on the value and feedback obtained from stakeholders. The other option is not valid, as it implies that releasing an Increment is mandatory at the end of each Sprint.