What is the timebox for a Sprint Planning event? (choose the best answer)

A.
Monthly.
Answers
A.
Monthly.
B.
8 hours for a one-month Sprint
Answers
B.
8 hours for a one-month Sprint
C.
Whenever ills done
Answers
C.
Whenever ills done
D.
4 hours for a one-month Sprint
Answers
D.
4 hours for a one-month Sprint
Suggested answer: B

Explanation:

According to the Scrum Guide, the timebox for a Sprint Planning event is 8 hours for a one-month Sprint, proportionally shorter for shorter Sprints. The other options are not valid, as they are either too long (such as monthly), too vague (such as whenever it's done), or too short (such as 4 hours for a one-month Sprint).