Question 231 - PSM I discussion
A Scrum Master is introducing Scrum to a new Team. The Team has decided that a Sprint Retrospective is unnecessary. What action should the Scrum Master take?
(choose the best answer)
A.
Comply with the decision of the self-managing team.
B.
Begin facilitating productive and useful Sprint Retrospectives.
C.
Call a meeting between the ScrumTeam and senior management
D.
Consult with the Product Owner to see how they feel about the situation.