Who creates the Definition of Done?

(choose the best answer)

A.
The Scrum Master
Answers
A.
The Scrum Master
B.
The Product Owner
Answers
B.
The Product Owner
C.
The scrum Team
Answers
C.
The scrum Team
D.
The Developers
Answers
D.
The Developers
Suggested answer: C

Explanation:

The correct answer is C. The Scrum Team creates the Definition of Done. According to the Scrum Guide1, "The Developers are required to conform to the Definition of Done, which is defined and evolves with the Scrum Team." The Definition of Done is a commitment by the Developers for the Increment, but it is also a shared understanding within the whole Scrum Team, including the Product Owner and the Scrum Master2. The Scrum Team collaborates to create and update the Definition of Done as needed, based on the product and organizational standards3. The Definition of Done is not imposed by any external authority or individual.

asked 23/09/2024
Asad yaseen
40 questions
User
Your answer:
0 comments
Sorted by

Leave a comment first