A Scrum Team is experiencing a growing list of impediments. Which techniques would be most helpful in this situation?

(choose the best two answers)

A.
As a Scrum Team, prioritize the list and work on them in order.
Answers
A.
As a Scrum Team, prioritize the list and work on them in order.
B.
The Scrum Master discusses the impediments with the Scrum Team.
Answers
B.
The Scrum Master discusses the impediments with the Scrum Team.
C.
The Product Owner should add the open impediments to the Product Backlog.
Answers
C.
The Product Owner should add the open impediments to the Product Backlog.
D.
Arrange a triage meeting with management.
Answers
D.
Arrange a triage meeting with management.
Suggested answer: A, B

Explanation:

The best two answers are A and B. As a Scrum Team, prioritizing the list and working on them in order is a good technique to tackle the impediments. This way, the team can focus on the most urgent and important issues first and avoid being overwhelmed by the number of impediments. The Scrum Master discusses the impediments with the Scrum Team is also a helpful technique, as it allows the team to share their perspectives, identify the root causes, and come up with possible solutions. The Scrum Master can also coach the team on how to remove or prevent impediments in the future.