Question 250 - PSM I discussion
A Scrum Team is experiencing a growing list of impediments. Which techniques would be most helpful in this situation?
(choose the best two answers)
A.
As a Scrum Team, prioritize the list and work on them in order.
B.
The Scrum Master discusses the impediments with the Scrum Team.
C.
The Product Owner should add the open impediments to the Product Backlog.
D.
Arrange a triage meeting with management.