List of questions
Related questions
Question 5 - PSM II discussion
Scrum requires a Definition of Done. Which phrases describe the purpose of the Definition of Done?
(choose the best three answers)
A.
It serves to track the percent completeness of a Product Backlog item during the Sprint.
B.
During the Sprint it helps the Developers identify the work remaining for an Increment to be ready for release by the end of a Sprint.
C.
It creates transparency into the state of the Increment when it is inspected at the Sprint Review.
D.
It guides the Developers when creating a forecast at the Sprint Planning.
E.
It provides a template for the documentation of the product Increment.
F.
It is a checklist to inspect whether the Developers have performed their tasks by the end of a Sprint.
Your answer:
0 comments