How should requirements be distributed when multiple Scrum Teams work on the same product?

(choose the best answer)

A.
They must be selected from one Product Backlog in such a way that each Scrum Team has an equal volume of requirements per Sprint.
Answers
A.
They must be selected from one Product Backlog in such a way that each Scrum Team has an equal volume of requirements per Sprint.
B.
The Scrum Teams pull in work from a shared Product Backlog in agreement with the Product Owner and the other teams.
Answers
B.
The Scrum Teams pull in work from a shared Product Backlog in agreement with the Product Owner and the other teams.
C.
The Scrum Team with the highest velocity pulls items from an overall Product Backlog first
Answers
C.
The Scrum Team with the highest velocity pulls items from an overall Product Backlog first
D.
The Product Owner decides by providing each team with its own Product Backlog.
Answers
D.
The Product Owner decides by providing each team with its own Product Backlog.
Suggested answer: B

Explanation:

When multiple Scrum Teams work on the same product, they share one Product Backlog that contains all the requirements for the product. The Product Owner is responsible for ordering and refining the Product Backlog items, but does not assign them to specific teams. Instead, the Scrum Teams pull in work from the Product Backlog in agreement with the Product Owner and the other teams, based on their capacity, skills, dependencies, and Sprint Goals. This way, the Scrum Teams can self-organize and collaborate to deliver a coherent and valuable product Increment.

The Scrum Guide, November 2020, p. 7-8