Question 9 - PSM II discussion
How should requirements be distributed when multiple Scrum Teams work on the same product?
(choose the best answer)
A.
They must be selected from one Product Backlog in such a way that each Scrum Team has an equal volume of requirements per Sprint.
B.
The Scrum Teams pull in work from a shared Product Backlog in agreement with the Product Owner and the other teams.
C.
The Scrum Team with the highest velocity pulls items from an overall Product Backlog first
D.
The Product Owner decides by providing each team with its own Product Backlog.