A Scrum Team has been using the Daily Scrum to report Sprint progress to the Product Owner, because the Product Owner wants to track what every Developer is working on every day. What is the best thing for the Scrum Master to do?
(choose the best answer)
A.
Coach the Product Owner and the Developers on the purpose of Scrum events and let them figure out how to deal with this situation.
B.
Start attending the Daily Scrum so that whenever the Developers have a conflict with the Product Owner, the Scrum Master can resolve the conflict
C.
Nothing. The Product Owner can continue to track progress at the Daily Scrum.
D.
Ask the Product Owner to stop attending the Daily Scrum.