Five new Scrum Teams have been created to build one product. A few of the Developers ask the Scrum Master who will coordinate the work between the different Scrum Teams. What should the Scrum Master do?
(choose the best answer)
A.
Visit the five Scrum Teams each day to facilitate alignment and synchronization of their Sprint Backlogs.
B.
Collect the Sprint tasks from the teams at the end of their Sprint Planning and merge that into a consolidated plan for the entire Sprint.
C.
Teach the Product Owner to work with the lead developers on ordering Product Backlog in a way to avoid too much technical and development overlap during a Sprint.
D.
Teach them that it is their responsibility to form Scrum Teams with the skills and knowledge to create an Increment by the end of every Sprint.
E.
Advise the teams to reduce interdependence by working in separate branches and organizing a specific Sprint every four development Sprints to manage integration.
Your answer: