Eight months ago your company started developing a new product consisting ot several major components. You are the Scrum Master on the team building the 'core' component of the product; your component also integrates all the other components.

The Scrum Teams work in monthly Sprints, and the team has forecast that it will deliver the integrated product in three Sprints. Recently the team's progress slowed because of changes to the other components that they integrate. The program manager is extremely upset when they find out that the team will need two more Sprints. The project managers of the other components confirm their adherence to the original forecast.

As a Scrum Master, what could you do to help the Product Owner?

(choose the best answer)

A.
You calculate how many additional developers it would take to increase velocity to make the original date. You inform the program manager of the additional budget for these developers. This would then allow meeting the original forecast
Answers
A.
You calculate how many additional developers it would take to increase velocity to make the original date. You inform the program manager of the additional budget for these developers. This would then allow meeting the original forecast
B.
You remove all items from the Product Backlog for which development is forecast to be beyond the expected date.
Answers
B.
You remove all items from the Product Backlog for which development is forecast to be beyond the expected date.
C.
You suggest working with the program manager and the project managers of the other components on the ordering and the value of your open Product Backlog items to redefine the possible delivery date.
Answers
C.
You suggest working with the program manager and the project managers of the other components on the ordering and the value of your open Product Backlog items to redefine the possible delivery date.
D.
You lengthen your Sprints to accommodate the delays.
Answers
D.
You lengthen your Sprints to accommodate the delays.
Suggested answer: C

Explanation:

As a Scrum Master, you could help the Product Owner by suggesting working with the program manager and the project managers of the other components on the ordering and the value of your open Product Backlog items to redefine the possible delivery date. This would allow you to collaborate with the stakeholders and align on the expectations and priorities of the product. You could also inspect and adapt your integration process and communication channels with the other teams to minimize the impact of changes and dependencies.

The Scrum Guide 2020, section ''The Scrum Master''

The Scrum Master Learning Path, module ''The Scrum Master as a Coach''

The Professional Scrum Master II Course, topic ''Stakeholder Management''