You are the Scrum Master of a Scrum Team that is new to Scrum. The Product Owner comes to you halfway through the Sprint and says, 'l do not feel like the De-velopers will be able to meet the forecast that they developed during Sprint Planning.' What should you do in this situation?
(choose the best answer)
A.
Coach the Product Owner that achieving the Sprint Goal is the Scrum Team's objective. A forecast is only used to initially estimate the effort required to reach the Sprint Goal.
B.
Agree to help the Product Owner by having a discussion with the Developers about the importance of meeting their forecast.
C.
Add more people to the Scrum Team to meet the Product Owner's ex-pectations.
D.
Talk to the Developers. Challenge and inspire them to complete all of the work so that they meet their forecast.