You are a Scrum Master helping to establish five Scrum Teams that will be building a product.

You discuss with them the high level of integration that the product Increment will require by the end of their first Sprint. It is a highly anticipated product, both by consumers and by the organization. Of the options raised by the future Scrum Team members, which option do you encourage?

(choose the best answer)

A.
Each Scrum Team provides a separate Increment with the functionality added by the individual team. The Sprint Review is used to identify the work needed to integrate with the other Scrum Teams. This work is then added to the Product Backlog.
Answers
A.
Each Scrum Team provides a separate Increment with the functionality added by the individual team. The Sprint Review is used to identify the work needed to integrate with the other Scrum Teams. This work is then added to the Product Backlog.
B.
Each Scrum Team delivers done Increments in its own area of responsibility. Upon functional acceptance at the Sprint Review, the code is isolated for future stabilization. The release date is adjusted according to the expected work and time of such integration phase.
Answers
B.
Each Scrum Team delivers done Increments in its own area of responsibility. Upon functional acceptance at the Sprint Review, the code is isolated for future stabilization. The release date is adjusted according to the expected work and time of such integration phase.
C.
In the first Sprint, integration is less important. The goal is to deliver business value. Functionality that is not integrated with the work of other Scrum Teams by the end of a Sprint is still reviewed to assess its potential business value. It can still be released at the Product Owner's discretion, and silent consent of the stakeholders.
Answers
C.
In the first Sprint, integration is less important. The goal is to deliver business value. Functionality that is not integrated with the work of other Scrum Teams by the end of a Sprint is still reviewed to assess its potential business value. It can still be released at the Product Owner's discretion, and silent consent of the stakeholders.
D.
All Scrum Teams agree on a shared Definition of Done that describes all work needed to deliver an Increment that is the integrated sum of the work from all Scrum Teams.
Answers
D.
All Scrum Teams agree on a shared Definition of Done that describes all work needed to deliver an Increment that is the integrated sum of the work from all Scrum Teams.
Suggested answer: D

Explanation:

The Scrum Guide states that ''the moment a Product Backlog item meets the Definition of Done, an Increment is born'' and that ''the Increment is the sum of all the Product Backlog items completed during a Sprint and the value of the increments of all previous Sprints''. Therefore, to deliver a product Increment that is integrated and potentially releasable, all Scrum Teams must have a shared understanding of what ''Done'' means and ensure that their work meets that standard. This also enables transparency, inspection, and adaptation across the Scrum Teams.

The Scrum Guide, section 3.4 (The Increment), page 10

The Scrum Master Learning Path, module 5 (The Increment), lesson 1 (What is an Increment?) and lesson 2 (Definition of Done)

asked 23/09/2024
Amidou Florian TOURE
33 questions