Question 23 - AD0-E903 discussion
The marketing team should begin working on a task on September 23, complete it within 2 weeks and take approximately 10 hours over that time span to execute the deliverable.
Which task settings need to be configured to meet these requirements?
A.
The Task Constraint should be set to Must Start On with Planned Time set to 2 weeks and Duration set to 10 hours.
B.
The Task Constraint should be set to Must Start On with Planned Hours set to 10 hours and Duration set to 2 weeks.
C.
The Task Constraint should be set to Start Date of September 23 with Planned Hours set to 10 hours and Issue Duration set to 2 weeks.