Question 24 - AD0-E903 discussion
A task was originally planned with a 10-day duration and 40 planned hours. The client needs it done in 3 days.
What task setting needs to change to allow 4 users to complete this in less than 3 days?
A.
Change the Task Duration Type to Effort Driven
B.
Change the Task Duration Type to Calculated Work
C.
Change the Task Constraint to Fixed Dates
D.
Change the Task Constraint to As Soon As Possible