A task owner has Time Off logged in Workfront for all of next week. The owner has a task that is planned to start and is due while she is out.

What action should the task owner take?

A.
Set the task condition to At Risk.
Answers
A.
Set the task condition to At Risk.
B.
Update the Commit Date on the task.
Answers
B.
Update the Commit Date on the task.
C.
Work on the task and complete it in the given duration.
Answers
C.
Work on the task and complete it in the given duration.
Suggested answer: B

Explanation:

In Workfront, when a task owner is unavailable due to time off, they can update the Commit Date to reflect when they are available to work on the task. This prevents delays and ensures the task is completed within a revised timeline. The Commit Date feature is designed to accommodate personal schedules and ensure tasks are accurately tracked without putting the task 'At Risk' unnecessarily.