Given this information regarding a Task:

* Planned Start Date: May 14

* Actual Start Date: May 14

* Planned Completion Date: May 20

* Projected Completion Date: May 22

* Percent Complete: 50%

* Duration: 5 Days

* Planned Hours: 8 Hours

* Status: In Progress

If today's date were May 19, what would be the Task's progress status?

A.
Behind
Answers
A.
Behind
B.
On Time
Answers
B.
On Time
C.
At Risk
Answers
C.
At Risk
Suggested answer: C

Explanation:

In Workfront, when the projected completion date exceeds the planned completion date and the task is only 50% complete by May 19, it is automatically flagged as 'At Risk.' This alerts the project manager that the task is not progressing according to the original plan, potentially causing delays in the project timeline.