Question 30 - AD0-E903 discussion
The last 5 tasks in a project need to happen within 10 days of the end of the project.
Which Task Constraint should the project manager use to configure this timeline without setting specific dates?
A.
Start No Later Than
B.
Must Start On
C.
As Late As Possible
Your answer: