The last 5 tasks in a project need to happen within 10 days of the end of the project.

Which Task Constraint should the project manager use to configure this timeline without setting specific dates?

A.
Start No Later Than
Answers
A.
Start No Later Than
B.
Must Start On
Answers
B.
Must Start On
C.
As Late As Possible
Answers
C.
As Late As Possible
Suggested answer: C

Explanation:

In Workfront, the 'As Late As Possible' task constraint ensures that tasks are scheduled as close to the project's end date as possible. This is useful when specific start dates are not necessary, but tasks need to happen near the end of the project timeline. This constraint allows for flexibility while still ensuring that the tasks are completed within the required time frame.